OVERNIGHT ROAD CLOSURE – LEONARDS MOOR B3181 (WILLAND)/CHAPEL HILL CROSSROADS: 18 & 19 AUGUST

Devon Highways have issued information about resurfacing works they are carrying out on B3181 Leonard Moor from 18 August. The road will be closed to vehicles on each working night Thursday and Friday between the hours of 7pm and 6am.
Due to the nature of the works a road closure is required and the diversionary route for traffic will be via the M5 and B3181 via Cullompton. The existing weight restriction on B3181 from Cullompton to Willand will be suspended both nights. The diversion route will be fully signed throughout.
Devon Highways apologises in advance for any inconvenience caused, including construction noise and will endeavour to keep all disruption to a minimum.
The planned programme for the delivery of the work is:
• Thursday 18th August
Removal of the existing road surface at the crossroads of B3181 and Chapel Hill. Please note – this will be the noisiest part of the works, but Devon Highways will attempt to keep disruption to a minimum to all residents and businesses.
• Friday 19th August
Resurfacing and relining works.
• Saturday 20th August
Road reopens as normal.

Daily information will be posted on Devon Alerts social media and can be found here: https://www.facebook.com/DevonAlert  or on Twitter:  @ DevonAlerts